The Knockdown Rebuild Process in Sydney, Step by Step: Plans, Demolition and Approvals
The order of a knockdown rebuild in Sydney, from site checks and plans to approvals, demolition, building and moving in.
The short version
A knockdown rebuild follows a set order. You check the site, design the new home, get approval, demolish, build and move in. Doing the steps in the right order saves time and money.
In short
Plans and approvals come first. Demolition usually starts only once approvals are in place and the builder is ready.
- Check the site and your council's rules
- Set a budget and a clear brief
- Prepare drawings and reports, including BASIX
- Get approval through a development application or a complying development certificate
- Demolish, build, pass inspections and move in
What is a knockdown rebuild?
A knockdown rebuild means demolishing your existing home and building a new one on the same block. You keep the land and the location. You replace the house.
People choose it when the block is right but the home is old, small or poorly laid out.
The steps, in order
Step 1: Check the site and the rules
Start with a land survey and a planning certificate from your council. These show boundaries, levels, zoning, heritage and other controls. Check for buried services and have the soil tested.
Step 2: Set your budget and your brief
Decide what you want in the new home, how much you can spend and how long you can live elsewhere. Include demolition, approvals, rent and a buffer, not only the build.
Step 3: Design the new home
Your drafter turns the brief into a design that suits the block and the planning rules. You review the plans and refine them until you are happy.
Step 4: Prepare the drawings and reports
Approval needs a full set of drawings and supporting documents.
- Site plan, floor plans, elevations and sections
- BASIX certificate
- Structural and stormwater design
- Soil or geotechnical report
- Reports for bushfire, flood or heritage where they apply
- Demolition and waste details
Step 5: Get approval
Your council or a private certifier assesses the application. The path depends on your lot and design. See the next section for how a development application and a complying development certificate differ.
Step 6: Lock in the builder and the construction certificate
Before building starts you need a construction certificate and a principal certifier. Choose a licensed builder, read the contract carefully and check the insurance and payment schedule.
Step 7: Demolish and prepare the site
Once approvals and arrangements are in place, the old house comes down.
- Disconnect water, sewer, power and gas
- Remove asbestos through licensed people if it is present
- Protect trees and neighbouring properties
- Install erosion and sediment controls
- Clear and level the site
Step 8: Build the new home
The builder works through footings, frame, lock up and fit out. Your certifier inspects key stages. Keep in touch with the builder about any changes, because variations add cost and time.
Step 9: Finish, certify and move in
When the work is done, the certifier checks it and issues an occupation certificate. Then you can move in. Plan for final fixes, landscaping and your move date.
Approval pathway: development application or complying development
The approval path affects how long you wait and how much flexibility you have.
Development application (DA)
Council assesses the design against its planning rules and can ask for changes. It suits sites with heritage, odd shapes or designs that go beyond fixed standards. Read more in our guide to the development application process.
Complying development certificate (CDC)
A council or private certifier approves the design if it meets fixed standards. It can be quicker, but the lot and the design must tick every box. Not every site qualifies. See what a complying development certificate is.
A drafter can check which path your block and design suit before you commit.
What affects how long a knockdown rebuild takes
- How quickly you finalise the design
- Whether council asks for more information
- The approval path you use
- Asbestos, trees or difficult access on the site
- Weather and builder availability
- Changes you make once building has started
Because the house is demolished, you will need somewhere else to live for the whole build. Plan rent, storage and moving costs from the start.
Pros and cons of a knockdown rebuild
Pros
- A design made for you and the block
- New structure, services and finishes
- Better energy performance
- You stay in a suburb you already like
Cons
- You must move out for the whole build
- Demolition and approvals add steps and cost
- Heritage and planning controls may limit what you can do
- A longer, more complex project than a small renovation
Mistakes to avoid
- Booking demolition before approvals are in place
- Skipping the survey and soil test
- Not checking for asbestos until demolition begins
- Leaving out temporary accommodation from the budget
- Signing a builder contract before the drawings are final
- Making changes during construction without pricing them first
What to do next
Send us your address and your brief. We will check which approval path suits your block, prepare the drawings and reports and quote a fixed fee before any work begins.
Compare the full budget in our guide to knockdown rebuild costs in Sydney, or see our new home and knockdown rebuild drafting service.
Knockdown rebuild process questions Sydney homeowners ask
What is the first step in a knockdown rebuild?
Check the site and the rules. Get a survey, ask council for a planning certificate and find out about heritage, flood, bushfire and buried services.
Do I need approval to demolish my house?
Yes, demolition needs approval. It can be part of the same application as the new home or handled separately, depending on your site.
Should I choose a builder before or after the plans?
Either can work. Some people get plans first and then compare builders. Others choose a builder who offers design and construction. Make sure the drawings suit your block and the contract is clear.
Who inspects the work?
A principal certifier checks key stages and issues the occupation certificate when the home is finished.
Can I live in the house during a knockdown rebuild?
No. The house is demolished, so plan to live elsewhere for the whole build.
How do I know if my block can have a CDC?
A drafter can check your lot against the fixed standards. If the site or design does not fit, a development application is the usual path.